The Ministry of Infrastructure Development (MID) is pleased to announce that the Noro Roads Improvement has now reached 90 percent physical completion.
The work is funded by the World Bank under the Second Solomon Islands Roads and Aviation Project (SIRAP2) and is being implemented by MID. It remains on track to deliver safer and more reliable road infrastructure for the people of Western Province by the end of December 2025.
Recent construction highlights include: (i) completing high-strength concrete pavement on Port Entry, with the section temporarily closed to traffic to allow for concrete curing for 28 days; (ii) commencing concrete-lined drainage works on Fergusion Road, with drain covers prefabricated off-site; and (iii) sealing Custom Road, Baru Feeder Road, Bonito Drive, Catholic Road, and Tausinga Road with double bituminous surface treatment, with road shoulders paved on Noro Highway, Industrial Road, and Noro-Munda Road.