Construction of the new Air Traffic Control Towers (ATCT) at Honiara and Munda International Airports are progressing well under the Second Solomon Islands Roads and Aviation Project (SIRAP2). Funded by the World Bank and implemented by the Ministry of Communication and Aviation (MCA), the towers are being constructed by China Civil Engineering Construction Corporation, with Egis Asia providing construction supervision.
A key milestone has been achieved at both sites with the successful transition from substructure to superstructure works. Following backfilling, work has continued to the ground and first-floor levels. Current activities include masonry block works, reinforcement detailing, and formwork installation for columns and shear walls.
At Honiara (Lot 1), masonry block wall is being constructed on the ground floor, columns have been cast up to the structural slab. Preparations are ongoing for shear wall casting and reinforcement detailing on the first-floor beams and slabs.