Steady progress has been made on the upgrades to Santa Cruz Airfield, funded by the World Bank under the Second Solomon Islands Roads and Aviation Project (SIRAP2) and implemented by the Ministry of Communication and Aviation (MCA).
The works are 43 percent complete, and the first phase of activities is scheduled to be completed by mid-April 2025. This will include subgrade treatment and subbase and base course construction for 700 m of the entire 1,310 m runway. In addition, clearing and preparation works for the second phase has commenced at the eastern end of the airfield.
Last week, officers from MCA and the Ministry of Lands, Housing and Survey conducted a land survey at the western end of the airfield to confirm boundary alignments. Once completed, a Memorandum of Understanding will be signed with landowners to facilitate the planned airfield extension.